摘 要:對于新建、擴建發(fā)電機組,在基建調(diào)試過程中必須對電流互感器(CT)的變比、準確級、接線、極性等進行檢查確認。對調(diào)試過程中極性判別及接線檢查、伏安特性及10%誤差曲線校核、倒送電及整套啟動過程CT檢查進行了原理分析,并給出了具體調(diào)試步驟,確保CT的接線、極性等完全正確。
關(guān)鍵詞:基建調(diào)試;電流互感器;極性檢查
中圖分類號:TM452 文獻標識碼:A 文章編號:1007-3175(2020)10-0051-04
Study on the Commissioning Method of Current Transformer in the Construction Period of Power Plant
WANG Si-cong, LUO Kai, ZHANG Qing
(China Datang Corporation Science and Technology Research Institute Co.,Ltd,
Datang Northwest Electric Power Test & Research Institute, Xi'an 710021, China)
Abstract: For the newly built and expanded generator sets, the transformation ratio, accuracy level, wiring, polarity of current transformer(CT) must be checked and confirmed during the process of infrastructure commissioning.The principle analysis of polarity discrimination and wiring inspection, volt-ampere characteristics and 10% error curve verification, reverse power transmission and CT inspection of the entire start-up process during the debugging process are carried out, and specific debugging steps are given to ensure the wiring and polarity of the CT are completely correct.
Key words: infrastructure commissioning; current transformer; polarity check
參考文獻
[1] 趙盛,董新叢. 電流互感器極性詳解[J]. 工程建設(shè)與設(shè)計,2018(22):71-72.
[2] 高大全,唐大洪,李波. 現(xiàn)場正確判定電流回路極性的方法及應用[J]. 冶金動力,2019(9):24-28.
[3] 鮮萬春. 電流互感器的接線及極性測試的分析[J].科技資訊,2017,15(33):41-42.
[4] 陳冬蕾,燕寶峰,茍曉桐,趙磊. 電流互感器極性檢查現(xiàn)場測試常用方法[J]. 內(nèi)蒙古石油化工,2015,41(8):66-68.
[5] 蘇果. CT伏安特性曲線及10%誤差校驗方法探討[J]. 水電站機電技術(shù),2018,41(5):16-18.
[6] 甘園林. 電流互感器CT 10%誤差校驗及舉例[J].化學工程與裝備,2016(9):228-230.
[7] 顧建華,彭前位,盛利華. 利用變壓器短路試驗電流檢查差動保護二次電流回路接線[J]. 電世界,2017,58(8):14-15.
[8] 王霏霏. 利用勵磁涌流校核差動保護極性的可行性研究與實踐[J]. 湖南電力,2016,36(6):26-29.